Progress Billing and Retainage for Contractors

Last updated November 19, 2026

Progress billing means you bill a job in pieces as the work gets done, usually once a month, instead of one invoice at the end. On most commercial jobs each bill is a pay application (often on the AIA G702 and G703 forms) that shows the contract, the percent complete on every line, and the retainage the owner is holding back until the job is finished. The hard part is not filling in one form. It is keeping every pay app, every change order and every dollar of retainage correct from the first bill to the last, and making sure your books say the same thing.

This page explains how progress billing and retainage work, where contractors usually get it wrong, and how BluePrint JC keeps it together with job costing and accounting.

How progress billing works

Every progress bill starts from the schedule of values: the contract amount split into lines, one per part of the work (site work, concrete, framing, electrical and so on). Each billing period you record how far along each line is. The bill for the period is the value of new work done since the last bill, plus any materials bought and stored for the job but not yet installed, if your contract allows billing for them.

Because each bill builds on the last one, the numbers are cumulative. Work completed to date is last period's total plus this period's work. If one bill is wrong, every bill after it carries the error forward.

The two AIA forms: G702 and G703

Most pay applications use two linked forms. Fill in the G703 first; its totals feed the G702. The most common reason a pay app is sent back is that the two do not agree.

  • G703 (Continuation Sheet) is the line-by-line detail. Each schedule of values line shows the scheduled value, work from previous applications, work this period, materials presently stored, total completed and stored to date, percent complete, balance to finish, and retainage.
  • G702 (Application and Certificate for Payment) is the one-page summary on top. It starts from the original contract sum, adds net change orders, takes the G703 totals, subtracts retainage and previous certificates, and arrives at the current payment due.

How retainage works

Retainage (also called retention) is a percentage of each payment that the owner holds back until the job is complete, to make sure the work gets finished and fixed. The percentage comes from the contract, and some state laws and public contracts limit it. Check your contract and your own advisers for the rules that apply to your job; this page does not give legal or tax advice.

Three things make retainage easy to lose track of:

  1. It piles up quietly. A small percentage per bill becomes a large balance by the end of a long job.
  2. It runs both ways. Your customer holds retainage from you (money owed to you), and you may hold retainage from your subcontractors (money you owe them).
  3. It has to be billed again. Retainage does not pay itself. At the end of the job, or at a milestone, you send a separate bill to release it, sometimes in parts.

Common progress billing mistakes

  • Billing a change order before it is approved, or forgetting to add an approved one to the contract sum.
  • Rounding differences between the G703 lines and the G702 total.
  • Billing stored materials without the backup the owner asks for.
  • Tracking retainage in a spreadsheet that never gets matched to the general ledger.
  • Forgetting to bill retainage release at all, so the money sits uncollected.
  • Over or under billing compared with the actual cost of the work, which shows up later on the WIP schedule your accountant or bonding company reviews.

How BluePrint handles progress billing and retainage

BluePrint JC keeps billing, job costing and accounting in one system, so a pay app is also the accounting entry. See accounting for the full picture.

  • AIA-style payment applications. Create a payment application from the job's budget lines, with a Schedule of Values (G703) and a Payment Application Summary (G702). Previous work is carried forward from earlier pay apps automatically.
  • Change orders on the summary. Approved change orders show on the payment application and change the contract sum.
  • Stored materials. Enter materials presently stored on each line, alongside work this period.
  • Retainage on every pay app. Set retainage on the job and BluePrint works out retainage this period and retainage held to date.
  • Retainage release. Bill retainage release as its own invoice when the time comes, in full or as a percentage of what is held, line by line.
  • PDF and email. Sending a pay app records it in the books, creates the PDF and emails your customer. Customers can also see invoices in the customer portal.
  • Retainage you hold from subs. Track retainage on subcontracts and release it when the sub has earned it. Subcontractors can submit bills and payment applications through the vendor portal. See subcontracts and change orders.
  • Reports that tie to the books. Retainage Receivable (what customers are holding from you) and Retainage Payable (what you are holding from subs) are both checked against the Balance Sheet. The Work in Progress (WIP) report shows over and under billing on active jobs, and AR Aging shows what is outstanding.
  • Other contract types. Besides progress billing, BluePrint bills cost-plus, time and materials, unit price and GMP contracts, plus deposit invoices and credit memos.

Frequently asked questions

What is progress billing in construction?

Billing a job in stages as work is completed, usually monthly, based on the percent complete of each line in the schedule of values, instead of one invoice at the end.

What is the difference between the AIA G702 and G703?

The G703 is the detailed continuation sheet with one row per schedule of values line. The G702 is the one-page summary that takes the G703 totals, subtracts retainage and earlier payments, and shows the amount due now.

What is retainage and when is it paid?

Retainage is a percentage of each payment held back by the owner until the job, or an agreed part of it, is complete. It is paid when you bill for its release and the owner approves it under the contract terms.

Can I bill for materials that are stored but not installed?

Often yes, if the contract allows it. They go in the "materials presently stored" column, and owners usually ask for proof such as invoices or photos. Retainage may apply to them too, depending on the contract.

How do I keep retainage matched to my books?

Record retainage on each pay app in the same system as your general ledger, and review a retainage receivable and payable report against the balance sheet each month. In BluePrint those reports do that check for you.